2022上半年系统集成项目管理工程师上午综合知识真题(71-75)

责编:胡媛 2022-05-28

为方便广大考生考后估分对答案,希赛网特向广大学员和网友搜集整理了2022上半年系统集成项目管理工程师上午综合知识真题(71-75),供大家参考。希赛网老师也将在考后进行真题答案解析,敬请广大考生关注。

A grid for mpping the probability of occurrence of each impact on project objectives if that risk occurs is used in (71).

(71)A.risk plan process

B.risk control process

D.risk response process

C.risk analysis process

Machine leanning a fundamental concept of (72) research since the field ´s inception,is the study of computer algorithms that improve automatically throgh experience.

(72)A. date center

B.artificial intelligence

C.edge computimg

D.lnternet Protocol Version 6

The project (73) processes include: develop project charter, develop project management plan,direct and manage project work,manage project knowledge,monitor and control project work,perform integrated change control and close project or phase.

(73)A.integration management

B.scope management

C.schedule management

D.resource management

(74)includes the process for incorporating the organization's quality policy regarding planning managing and controlling project and product quality  rquirements in order to meet stakeholders’objectives.

(74)A.Project risk management

B.Project communication management

C.Project stakeholder management

D.Project quality  management

(75)is  the process of monitoring the status of the project to update the projects costs and managing changes to the cost baseline.

(75)A.Control costs

B.Costs udates

C.Validate scope

D.Monitor comnunications


相关推荐:2022上半年系统集成项目管理工程师上午真题答案解析

热点推荐:2022上半年系统集成项目管理工程师真题及答案解析

更多资料
更多课程
更多真题
温馨提示:因考试政策、内容不断变化与调整,本网站提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!
相关阅读
查看更多

加群交流

公众号

客服咨询

考试资料

每日一练

咨询客服