2019下半年系统集成项目管理工程师考试英语题

责编:胡媛 2019-11-12

71、(  )contributes to monitoring and data collection by defining security monitoring and date collection requirements.

A、information continuity management

B、information catalogue management

C、information security management

D、information distribution management

72、(  )seek to perform root cause investigation as to what is Ieading identified trends.

A、incident management

B、problem management

C、change management

D、knowledge management

73、the (  ) is a graph that shows the relationship between two variables.

A、histograms

B、flowcharts

C、matrix diagrams

D、Scatter diagrams

74、(  )is the process of identifying individual project risks as well as source of overall project risk, and documenting their characteristics.

A、identify risks

B、monitor risks

C、impIement risks responses

D、plan risk management

75、work performance information is circulated through(  ) processes.

A、 planning

B、 change

C、 improvement

D、 communication

相关推荐:2019下半年系统集成项目管理工程师上午真题及答案解析

热点推荐:2019下半年软考真题及答案解析(汇总)

更多资料
更多课程
更多真题
温馨提示:因考试政策、内容不断变化与调整,本网站提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!