71、( )contributes to monitoring and data collection by defining security monitoring and date collection requirements.
A、information continuity management
B、information catalogue management
C、information security management
D、information distribution management
72、( )seek to perform root cause investigation as to what is Ieading identified trends.
A、incident management
B、problem management
C、change management
D、knowledge management
73、the ( ) is a graph that shows the relationship between two variables.
A、histograms
B、flowcharts
C、matrix diagrams
D、Scatter diagrams
74、( )is the process of identifying individual project risks as well as source of overall project risk, and documenting their characteristics.
A、identify risks
B、monitor risks
C、impIement risks responses
D、plan risk management
75、work performance information is circulated through( ) processes.
A、 planning
B、 change
C、 improvement
D、 communication