● __(71)__ techniques are used to find ways to bring project activities that are behind into alignment with the plan by fast tracking or crashing the schedule for the remaining work .

(71)A. Schedule forecasts

B. Schedule compression

C. Change requests

D. Data analysis

● Generally, the contract claim can be settled amicably through negotiation. If no compromise can be reached, the dispute can be settled by __(72)__.

(72)A. negotiation

B. the court

C. lawyer

D. arbitration

● The organization shall undertake change in a planned and systematic manner, taking account of the review of the potential consequences of changes and taking action as necessary, to ensure the integrity of goods and services are maintained. This is called (  ).

(73)A. control of changes

B. control of plans

C. control of accounts

D. control of service

● Much of the effort of cost control involves analyzing the relationship between the consumption of project funds and the work being accomplished for such expenditures. The key to effective cost control is the management of the approved (  ).

(74)A. schedule baseline

B. cost baseline

C. cost output

D. cost input

● The top management of a company will review the organization’s management system, the management review will include consideration of :

( a ) customer feedback on quality

( b ) processes performance and product conformity

The purpose of management review is (  ).

(75)A. control of customers

B. control of measurements

C. control of qualities

D. control of opportunities



点击注册会员>>>即可获取信息系统监理师免费在线真题、观看免费公开课!

真题自测:信息系统监理师历年真题汇总

热点推荐:2021年软考报名时间及入口汇总表(全国)

相关推荐:2021年软考考试时间安排

更多资料
更多课程
更多真题
温馨提示:因考试政策、内容不断变化与调整,本网站提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!
相关阅读
查看更多

加群交流

公众号

客服咨询

考试资料

每日一练

咨询客服